Posted by – Steve Cohen, Director of Community Development
It has been a long two-year wait, but The Parkways project is now ready to take off. The property is located just west of Adams Road, south of the Forester Square Condominiums.
The foundation of the first building has been poured and framing will start this month. The ten townhouse units within this first building are expected to be ready for lease by June 2016.

The developer, Moceri Companies, plans to construct buildings within the project from east to west having a new building ready for occupancy every 45 to 60 days, weather permitting. The $46 million project will ultimately consist of 76 townhouse units, 72 stacked flat units, and a three-story 160 unit senior housing complex.